At lunch time, the painters were finishing off the paint job. The lower eaves are now painted too. Just hope it won't rain, as the roof tiles are not in place yet due to the safety railing and rain can ruin the paint job.
They will be back once the flooring is done, to finish off the skirting.
I have not inspect it yet, but looks like they did a good job on the paint.
Next two weeks I hope would be the finishing off all electrical and data cabling work, as well as shower screens. The main bathroom vanity basin should also be in.
Toilets and bathroom mirrors I expect to go in too.
16 & 17 of May are the upstairs flooring installation days. I expect floor tiles to follow the week after.
Then, PCI by end of May.