Friday, 19 April 2013

Front door slab

By lunch time, the front door slab formwork was now in place. I hope the concrete would be poured in today or Monday.

The back laudry steps landing also has its formwork in place.

The garage door also installed. Will have closed picture later, as workers were going in and out.

The bedroom sliding door rails installed.

Painting is still in progress. Possible paint end date is end of next week.