Saturday, 16 February 2013

Bricks Tagged to frame


The bricks are now tagged to the frame all around the house.

The balcony railing posts are now in place too.


Saturday, 19 January 2013

Roof Trusses started

Looks like half of the top roof trusses are installed. Hopefully it will be completed on Monday and sarking installed, followed by the roof tiles done by end of the week.

The gutters and eaves are also delivered.






Main entrance doorway





Thursday, 13 December 2012

Second floor done.

Upon visit this afternoon, looks like the second level is done. I hope tomorrow we will have the roof thrusts done. I recall our SS mentioning crain coming on Friday to lift them up.




Internal plumbing in progress

Back of house


Kitchen island plumbing

Backyard outdoor tap

Hot water plumbing point


View of the hallway towards the main door.

Stairway (temporary steps)

Balcony and portico point

Looks like there is a small issue with the location of air-con ducting wall position. They have placed it in one of the bedrooms, rather than on the other side, in the upstairs living room corner. (see pic below).

I did send a pic and the plan to our SS and explained that this corner wall needs to move on the other side like on the plans. I'm sure he will attend to it before roof is installed or "it's too late".



Thursday, 6 December 2012

Lower frames started today

Had a quick visit at lunch time today, and as expected, the frames are up!

This is a very exciting moment, as we can now visually see where things are and how big the rooms will be, not to mention, how big the house will end up.