Tuesday, 7 May 2013

Shower screen done

Had a meeting with our SS yesterday (He was going to postpone yet again!) and discussed about the driveway changes and the power pole ground level. Since the front yard ground will be levelled down to the level of the kerb, I had to inform our SS and make sure the power pole was installed at the new level.

Today, the ensuite shower screen is in place now, as well as all of the the bathroom mirrors.



Main bathroom shower screen ready to be installed. But I think it is the wrong size! Too wide.

The main vanity basin still missing (sitting on the floor next room), with wall-to-wall mirror. The towel holder visible in the background, will move to the left hand side.

A close-up of the laundry taps

The electrical box is also installed with the fuse boxes and thr 3-phase power.

Tuesday, 23 April 2013

Front slab & painting

Looks like on Monday the painters have finished their work.

The front slab concrete was also poured in on Monday

Now that the front slab is one, tiles should be next for them, once fully dried.


The back laundry steps done.

Front door undercoat done.


Few pictures of the internal paint and door handles.

Internal garage door with lock


Linnen



Bathroom accessories installed.
Ensuite

Toilet

Main bathroom

What Da! Towel rail behind and along the way! Some people have no common sense. Doh! This will have to be changed. Will move it to the wall on the left of basin.

Clothes. Whos? Why? LOL!

Friday, 19 April 2013

Front door slab

By lunch time, the front door slab formwork was now in place. I hope the concrete would be poured in today or Monday.

The back laudry steps landing also has its formwork in place.

The garage door also installed. Will have closed picture later, as workers were going in and out.

The bedroom sliding door rails installed.

Painting is still in progress. Possible paint end date is end of next week.

Wednesday, 17 April 2013

Wet areas complete

The scaffolding is now down and the house can be seen.

Painters were running the second coat and painting the internal doors.




The laundry tub is installed

Rangehood ducting to outside is installed.

The main bathroom bath and ensuite spa are now installed. While there, the shower screen guy was measuring the shower areas. So, I expect that to happen by next week too.


The balcony railing and privacy screen is also installed.


The corner, under the stairs might need cornices put in.