I had a list prepared, as well as my PCI list, coloured paper tags, plans as well as electrical plans. All armed up and ready.
The PCI took from 7:30am till 9:00am, going together with the SS. He was already on site and marking few spots with his sticker tag.
We went through each room, thoroughly inspecting every wall, joint, edge, frame, architrave, skirting etc.
Most issues were paint related, that require putty and paint. Ceilings, doors and floor edges were also inspected and couple of tags placed.
All doors and windows opened (fully) and closed correctly, specially the sliding windows and doors.
Inspected the kitchen, the drawers and overhead doors etc.
Outside, I only found 3 places where 2-3cm length mortar need to be added, and a small man made round hole blocked. That's it.
Things that still need to finish off are:
-Stairway carpet
-Main bathroom shower screen
-Manhole in the garage (somehow missed)
-Skirtings to be puttied and painted
Over all, very happy with the result. As I have always said, the Site Supervisor did do his job very well. (Thanks Phillip). And I had no doubts.
I'm hoping on Wednesday or Thursday our private consultant to go through the house again with the SS and report back. For added peace of mind.
So, here are some photos from today.
Main entrance & hallway
Stairway
Formal Lounge
Formal Dining
Living Room & Kitchen (and our SS Phillip)
Upstairs Family Room & Hallway
Upstairs Family Room & Hallway
Ensuite Wash Basin, Toilet, Shower & Spa
Main Vanity
Main Bathroom Bath
Main Bathroom Shower
During this week and next, Masterton has to finish off the list above plus get the rainwater underground detention tank installed and connected.
Masterton also to install:
-Gas Meter
-Phone Box
Handover date; Friday 7th of June 2013.