Showing posts with label Wet Areas. Show all posts
Showing posts with label Wet Areas. Show all posts

Wednesday, 10 April 2013

Wet area floor tiles

All of upstairs wet area floor tiles are placed, waiting for grouting.

The spa and bath formwork also in place.

Ensuite corner spa

Ensuite floor

Main bath

Main bathroom

Toilet floor

The balcony floor tiles are also in place.


Also in place the front door landing, fixing the slant issue as expected.


Thursday, 4 April 2013

Wet area progress

Most of the wet area tiles are now done. I expect to finish off by end of the week. Yay! Painting should start next week or so.

Edges of the balcony tiled

Powder room tiles

Ensuite tiling in progress


Shower with feature section

Main toilet with concealed drain

Main bathroom tiles

Main bathroom vanity

Laundry tiles

Laundry door landing

Kitchen island splashback

Kitchen splashback (no grout yet)

The house as it stands today


Wednesday, 3 April 2013

Wet area flooring



I drove by yesterday, saw some work being done. Sand & cement being mixed. I guess preparing the wet area floor tiles. Also saw some concrete slabs and some tiles for the front door slab & steps area.

I hope wet area tiling will start today, though I did not see any tiles delivered, but they could be upstairs already.

Wednesday, 20 March 2013

Wet areas sealed

Looks like today all the wet areas have been sealed.

Laundry

Main Bathroom

Ensuite

Ensuite

Toilet

The balcony is also has the seal applied.


Few external power points are also installed.


All downpipes are now connected to the main stormwater tank system. (tank yet to be dug up and installed).