Friday, 10 May 2013

Power poll installed

We had our power poll installed today. This means we might have power during our PCI.


Power connection from the poll to the mains box

Another peep through the door handle opening...lol.

Thursday, 9 May 2013

Floor tiles almost done

Looks like the floor tiles are almost done. Edges and corners are what's left, then grouting.

A quick photo from the outside through a window.

No one there today, but I guess they have to give 24 hours for it to settle and dry before they can walk on them to complete the rest.

Wednesday, 8 May 2013

Floor tiling started

Floor tiling has started today and I presume it will be done by Friday.

A quick photo from back sliding door. Bit hard with glass reflections. 

Hopefully I'll be able to take better photos once all done. 

Tuesday, 7 May 2013

Shower screen done

Had a meeting with our SS yesterday (He was going to postpone yet again!) and discussed about the driveway changes and the power pole ground level. Since the front yard ground will be levelled down to the level of the kerb, I had to inform our SS and make sure the power pole was installed at the new level.

Today, the ensuite shower screen is in place now, as well as all of the the bathroom mirrors.



Main bathroom shower screen ready to be installed. But I think it is the wrong size! Too wide.

The main vanity basin still missing (sitting on the floor next room), with wall-to-wall mirror. The towel holder visible in the background, will move to the left hand side.

A close-up of the laundry taps

The electrical box is also installed with the fuse boxes and thr 3-phase power.

Driveway & Landscaping

Over the course of last week I had few driveway and landscaping people come in to measure and quote.

So far I had 1 quote for driveway and 1 for landscaping.

Driveway: coloured concrete $14,500 (Bark) or $15,500 (Colourbond Loft, to match).
Landscaping: $9500 with Sir Walter Buffalo (355sqm), 20 Tonne fill, retaining wall, paving, all machinery hire and man power.

New driveway kerb will move to the right. Half way from current path and extend another 1/2 size. The total width will be the length of the 2 middle fence sections.

More quotes should come in this week.

Saturday, 4 May 2013

Air-con and Robes

On Friday we had our Air-Con vents installed and controller.





Also the carpenters have finished off the robes with shelving and hangers.



All the plumbing is also complete, including kitchen sink and powder room.



Wednesday, 1 May 2013

Plumbing & Electricals

Today finally some work done.

We had the electrician come in and do all the light fittings, downlights, power switches and power points. Also done the toilet vents.

The plumber was finishing off the toilets and drainage for basins and kitchen sink.

Display downlight

Living room downlights

bathroom service hole vent in kitchen

Ensuite vent

Ensuite toilet installed

Spa sprout

Ensuite basin

Bath sprout

Shower head

Toilet installed

Under balcony now painted

The safety rails also have been removed.