Thursday, 11 April 2013

Paint undrcoat nearly done

Today the painters could have finished all paint undercoat, and they have as far as they could. But since the tilers did not finish, that means they will have to come back later to finish off the undercoat, extending the delay for another week by the time the paint is done. That is if the tilers are back sometime this week.

Another mess-up by Masterton? our Site Supervisor? or the sub-contractors; once they do some work, get paid by Masterton, then they move on to the next job, only to come back when they have extra time?

I only know this because at lunch time I drove by, and they painters were sitting having a break and when I asked about undercoat being finished today, they told me wet area tiles are still not finished. They did not look happy about it as they could have finished all the undercoat for sure.

I mean, they could just over paint, under where the tiles would go?

Well, at least I can say they are doing a good job and very delicate in their work, to what I can see.







Wednesday, 10 April 2013

Wet area floor tiles

All of upstairs wet area floor tiles are placed, waiting for grouting.

The spa and bath formwork also in place.

Ensuite corner spa

Ensuite floor

Main bath

Main bathroom

Toilet floor

The balcony floor tiles are also in place.


Also in place the front door landing, fixing the slant issue as expected.


Finally some work

Visiting the site during my lunch break, the painters were in doing the undercoat of the ceilings.

Still no work from the tilers, and the painters were a bit annoyed as they cannot finish off, if tiling is not complete in all the wet areas and they will be forced to come back.

Garage

Formal Dining

Main hallway

Kitchen

Ensuite

Tuesday, 9 April 2013

Work stopped

Friday, no work done. Monday, no work done. Tuesday, no work done.

Looks like work has stopped with wet areas only half done.

  • Laundry skirting tiles still not done.
  • Powder room skirting tiles not done.
  • Main bathroom bath still no tiles.
  • Main bathroom shower has no wall tiles.
  • Main bathroom skirting tiles not done.
  • Main bathroom basin not installed.
  • Bedroom 2 robe doors not installed yet.
  • few windows still have to architraves.

According to the SS, we should have had the painters on today. Yeah right!

Thursday, 4 April 2013

Wet area progress

Most of the wet area tiles are now done. I expect to finish off by end of the week. Yay! Painting should start next week or so.

Edges of the balcony tiled

Powder room tiles

Ensuite tiling in progress


Shower with feature section

Main toilet with concealed drain

Main bathroom tiles

Main bathroom vanity

Laundry tiles

Laundry door landing

Kitchen island splashback

Kitchen splashback (no grout yet)

The house as it stands today


Wednesday, 3 April 2013

Wet area flooring



I drove by yesterday, saw some work being done. Sand & cement being mixed. I guess preparing the wet area floor tiles. Also saw some concrete slabs and some tiles for the front door slab & steps area.

I hope wet area tiling will start today, though I did not see any tiles delivered, but they could be upstairs already.

Tuesday, 2 April 2013

Architraves nearly done

Visiting the site today noticed most of the door and window architraves are done.



Built in robe sliding doors are also nearly done

Main bath granite top is still missing, due to the fact that yesterday, the workers must have damaged or done a wrong cut, and now needs a new one. Saw odd cut granite top in the bin.